Counting down …

The van is scheduled to roll out of Jeff’s shop in about a week.  Here are week old pictures showing the progress.

  • Solar panels are installed but not yet secured.  The frame that Aluminess built isn’t wide enough to bolt the panels directly to the rack.  Jeff is going to fabricate clamps, four per panel, to hold the panels in place.
  • Cabinets are finished and bolted into the van.  The door faces are done, too, but won’t be installed until later.
  • The water tank (20 gallons), exterior water fill, water pump, and water filter are installed.
  • The slide out desk is partly built.  The last half of the desk surface is hinged and isn’t installed yet.
  • The toilet is mounted and will vent underneath the van to avoid cutting another hole in the side of the van.
  • The shower pan area is cut out but not installed yet.
  • The sink and cooktop have been test fit.  Unfortunately, the hoped for double sink won’t fit.  The counter is a few inches too shallow to fit a faucet with a double sink.  If we had known earlier, we would have made the cabinet a few inches deeper.
  • Exterior work lights and awning are installed.
  • The gray water tank is installed but not quite finished.
  • The propane is plumbed to the interior of the van.  RVI did a nice job mounting the regulator and the black iron gas line out of harm’s way.
  • The thermostat and battery monitor are mounted.
  • The bed foundation is built. Next, Jeff will weld the bed frame and hooks for the Metolius ladder.